面板的设计与生产,项目交期要求:40天。 项目按时完成 Design and manufacture a complex faceplate for the S3 &P3 . Critical lead time for this project: 40 days. Project done. S3 &P3
11/2019
青岛Qingdao& 东莞Dongguan, China
开始研发时间
In September, it began to enter the mold making process
06/2020
青岛Qingdao & 东莞Dongguan, China
We started to work on the Haier Water Heater. This product is a virtual reality device made by Haier.
08/2020
产品发布前成功完成
Product launch. We successfully finalised this project on time.
海尔官网:http://www.haier.com/
该产品获得了2022年红点奖